With a strong track record of success, we have completed a few projects for leading companies in the industry.
Some of our notable projects include:
Project 1: Boiler & Heat Exchanger Maintenance – Boiler RCC131 at Aqualectra Power Plant DW2B
Location: Nieuwe Haven Willemstad Curaçao | 2024
Customer Contact Person: Mr. Ruiz (Plant Manager Power Supply Chain)
- Complete disassembly, mechanical cleaning, thorough inspection, and full refurbishment of Boiler RCC131 and components.
- Advanced coating application to enhance durability and optimize heat efficiency.
- Rigorous testing, commissioning, and certification by the Government Steam Authority Inspector of Curaçao.
Project successfully delivered ahead of schedule with zero safety incidents.
Project 2: Boiler & Heat Exchanger Maintenance – Degassing Tank RBA902 at Aqualectra Power Plant DW2B
Location: Nieuwe Haven Willemstad Curaçao | 2024
Customer Contact Person: Mr. Ruiz (Plant Manager Power Supply Chain)
- Complete disassembly, mechanical cleaning, thorough inspection, and full refurbishment of Degassing Tank RBA902 and components.
- Advanced coating application to enhance durability and optimize heat efficiency.
- Rigorous testing, commissioning, and certification by the Government Steam Authority Inspector of Curaçao.
Project successfully delivered ahead of schedule with zero safety incidents.
Project 3: Boiler & Heat Exchanger Maintenance – Main Steam Header at Aqualectra Power Plant DW2B
Location: Nieuwe Haven Willemstad Curaçao | 2024
Customer Contact Person: Mr. Ruiz (Plant Manager Power Supply Chain)
- Complete disassembly, mechanical cleaning, thorough inspection, and full refurbishment of Main Steam Header and components.
- Advanced coating application to enhance durability and optimize heat efficiency.
- Rigorous testing, commissioning, and certification by the Government Steam Authority Inspector of Curaçao.
Project successfully delivered ahead of schedule with zero safety incidents.
Project 4: Industrial Piping & Pump Works at Ministry of Finance
Location: Pietermaai, Punda Willemstad Curaçao | 2024
Customer Contact Person: Mr. Bodak (Director Optimum Engineering & Consultant N.V.)
- Complete disassembly, mechanical cleaning, thorough inspection, and full refurbishment of two centrifugal chiller pumps and components.
- Grit blasting and advanced coating application to enhance durability and optimize efficiency.
- Rigorous testing and commissioning.
Project successfully delivered on schedule with zero safety incidents.
Project 5: Boiler & Heat Exchanger Maintenance – Main Steam Header at Aqualectra Power Plant DW2B
Location: Nieuwe Haven Willemstad Curaçao | 2024
Customer Contact Person: Mr. Ruiz (Plant Manager Power Supply Chain)
- Complete disassembly, mechanical cleaning, thorough inspection, and full refurbishment of Main Steam Header and components.
- Advanced coating application to enhance durability and optimize heat efficiency.
- Rigorous testing, commissioning, and certification by the Government Steam Authority Inspector of Curaçao.
Project successfully delivered ahead of schedule with zero safety incidents.
Project 6: Industrial Structural Works (Workshop & Onsite) – Shop fabrication of Steel and Copper Components for High Voltage (HV) and Low Voltage (LV) Installations in the Aqualectra Power Grid.
Customer Contact Person: Mr. Raphaela (Grid Manager Power Supply Chain)
Aqualectra Projects:
Courtyard Marriott
Boase
Luxury Apartments
One Mambo
- Design & Engineering – Detailed assessment to meet project specifications.
- Material Selection & Preparation – Sourcing high-grade steel and cutting, bending, and shaping components.
- Fabrication & Welding – Precision welding and assembly to ensure structural integrity.
- Surface Treatment & Coating – Grit blasting and application of protective coatings for corrosion resistance and longevity.
- Quality Control & Inspection – Rigorous testing to comply with industry standards and client requirements.
Our expertise guarantees precision, durability, and compliance, providing reliable solutions for power infrastructure projects.
Projects successfully delivered ahead of schedule with zero safety incidents.
Project 7: Industrial Piping & Pump Works at New ADC Building
Location: Otrobanda Willemstad Curaçao | August 2024 to March 2025
Customer Contact person: Mr. Ignacius (CEO Quality Construction “Q-Con”)
- Installation of pumps and a completely new piping system for fire protection and plumbing work.
Project completion is planned for end April 2025.
Project 8: Boiler & Heat Exchanger Maintenance – Auxiliary Boiler RCA902 at Aqualectra Power Plant DW2B
Location: Nieuwe Haven Willemstad Curaçao | 2025
Customer Contact Person: Mr. Ruiz (Plant Manager Power Supply Chain)
- Complete disassembly, cleaning, thorough inspection, and full refurbishment of Auxiliary Boiler RCA902 and components.
- Advanced coating application to enhance durability and optimize heat efficiency.
- Rigorous testing, commissioning, and certification by the Government Steam Authority Inspector of Curaçao.
Project in progress and on schedule.
Project 9: Boiler & Heat Exchanger Maintenance – Blow Down Tank at Aqualectra Power Plant DW2B
Location: Nieuwe Haven Willemstad Curaçao | 2025
Customer Contact Person: Mr. Ruiz (Plant Manager Power Supply Chain)
- Complete disassembly, cleaning, thorough inspection, and full refurbishment of Blow Down Tank and components.
- Advanced coating application to enhance durability and optimize heat efficiency.
- Rigorous testing, commissioning, and certification by the Government Steam Authority Inspector of Curaçao.
Project in progress and on schedule.
Project 10: Gas Turbine & Generator Maintenance – Gas Turbine Inspection at Curaçao Refinery Utilities “CRU”
Location: Isla Refinery Willemstad Curaçao | Year: 2025
Customer Contact Person: Mr. Hermelijn (Manager)
- Comprehensive disassembly, cleaning, thorough open inspection, and troubleshooting of Gas Turbine GT9 and its components, conducted in partnership with our U.S. collaborator, Baseload Power of Corpus Christi Texas USA.
Project in progress and on schedule.